The Project received planning approval from the Minister of Planning, NSW. This Project is commenced. A link to the approval is provided below.
MP10_0185 Northbank Industrial Facility
The Link to the project’s environmental assessment report is provided below.
The Link to the project’s Response to Submissions is provided below.
Aboriginal Cultural Heritage
Management Plan
In accordance with Condition 37 of Schedule 3 of MP 10_0185, the Department of Planning & Environment (now DPHI) approved the Aboriginal Cultural Heritage Management Plan on 16 March 2018. Link provided below.
EPBC 2021-9058
The project received approval under the Commonwealth Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)
Issued by the Department of Climate Change, Energy, the Environment and Water on 13 February 2025.
Link to the Approval and Approved plans is provided below.
MP07_0086
The project planning approval from the Minister of Planning, NSW. A copy of the current, Modified consolidated approval with conditions can be downloaded below.
Soil and Water
Management Plan
In accordance with Condition 8 of Schedule 3, the Department of Planning and Environment (now known as DPHI) approved the Updated Soil and Water Management Plan for Stage 1 on 19 April 2023. This can be downloaded below.
Updated Soil and Water Management Plan for Stage 1 of Tomago Industrial Estate
In accordance with Condition 8 of Schedule 3, the Department of Planning and Environment (now known as DPHI) approved the Updated Soil and Water Management Plan for Stage 3.1A on 9 October 2020. This can be downloaded below.
Addendum No.2 – Development of Stage 3.1A, Environmental Management Plan – Soil & Management Plan
In accordance with Condition 8 of Schedule 3, the Department of Planning and Environment (now known as DPHI) approved the Updated Soil and Water Management Plan for Stage 3 on 14 March 2025. This can be downloaded below
In accordance with Condition 1 of Schedule 3 of MP07_086. The Planning and Envioronment (now DPHI) approved the Estate Layout Plan for Stages 2 and 3 on 16 August 2023. This can be downloaded below.
In accordance with Condition 24 of Schedule 3 of Mp07_086, the Department of Planning and Environment (now DPHI) approved the Transport Verification Study for Stages 2 and 3 on 20 December 2023. This can be downloaded below.
In accordance with Condition 2 of Schedule 3 of MP 07_0086, the Department of Planning, House & Infrastructure approved the Design Guidelines including the Landscape Masterplan in accordance with Condition 36 of Schedule 3 of MP07_0086, for Stage 3 on 14 March 2025. This can be downloaded below